Performance Profile: Producing Gas Well |
|||||||||||||
|
|
||||||||||||
|
Problem:
The customer will produce from two
separate zones. One will be produced through the 2 7/8” 6.50 lb. L-80
EUE 8rd. tubing. The other zone will be produced through the casing. The
tight tolerances will make it very difficult to protect the O.D. of the
2 7/8” tubing with chemicals. |
|
||||||||||||
|
|
Solution:
CeRam-Kote 54® was selected for the O.D.
application of the tubing on this deep, high pressure, producing gas
well due to its high abrasion resistance, high surface lubricity, high
adhesion, and flexibility. |
||||||||||||
|
|
|||||||||||||